Tuesday, May 19, 2009

14:31

Yesterday's 5 minute tag-up took 14 minutes and 31 seconds - all is not smooth and research-land. It exposes a problem of no real time for team interaction besides the tag-up and emails. The more disruptive problem is planning around holidays (I have had ~1 holiday per week recently). One person on holiday in a two person team = no meeting. I have still called in, but have no work to report and can take no action as scrum master so there is little sense. We should have planned around them... next time Gadget, next time!

Short sprints + small teams + holidays = problems. 